Learn about the ongoing Public Works and Facilities repair projects to county roads, right of ways and facilities from damage caused by Hurricane Ian.
Last Updated: 05/07/2024 Category: Sales Tax Funded Category: Sidewalks Current Phase: Design Development
The BCC has requested a sidewalk be designed and constructed on Cleveland as part of the 2020 Sales Tax Extension.Last Updated: 05/07/2024 Category: Roadway Current Phase: Construction
The purpose of this project is to resurface Charlotte County roadways in the following districts: Greater Port Charlotte, Pirate Harbor, Woodland Estates, Road and Bridge.Last Updated: 05/07/2024 Category: Roadway Current Phase: Planning and Project Approval
Flamingo/Edgewater Widening
Babcock Ranch CCSO District 5 Office
Last Updated: 05/03/2024 Category: County Facilities Current Phase: Construction
The 12,000 square foot building shell has been completed by Kitson Partners of Babcock Ranch in partnership with Florida Premier Contractors. The interior work has started.Last Updated: 05/03/2024 Category: County Facilities Current Phase: Construction
This 12,000 square foot three-bay facility will be a state-of-the art with hurricane impact rated bi-fold doors for additional protection. Interior build-out has started.Englewood East/Gulf Cove MSBU's Bridge Rehabilitations - #014082 and #014088
Last Updated: 05/03/2024 Category: Bridges Current Phase: Construction
Englewood East/Gulf Cove MSBU's Bridge Rehabilitations Design Services- Bridges 014082 and 014088
Sheriff District 4 HQ, Training Facility and K9 Unit
Last Updated: 05/03/2024 Category: County Facilities Category: Sales Tax Funded Current Phase: Construction
Construction of a replacement District 4 Headquarters Facility with a training component and K9 kennel/training area replacing existing facilites. The district office will utilize the prototype layout from District 1. The training building area will be incorporated into a single facility. The facility will be constructed at the Airport Road Annex site, replacing the existing Sheriff's Training, Supervisor of Election and old Transit Facility .Family Services Center - Phase 2
Last Updated: 05/03/2024 Category: Sales Tax Funded Category: County Facilities Current Phase: Turnover and Closeout
Completed the Human Services integrated services model with Phase 2 following the completion of Phase 1. Phase 2 enabled youth services to be constructed as a separate building on the campus. In Phase 2 of the FSC project, the Human Services' staff offices were constructed along with critical shared support facilities, maker space, and expanded services.Ainger Creek Boat Ramp Replacement
Last Updated: 05/03/2024 Category: Parks And Recreation Current Phase: Design Development
This project consists of evaluating the site to improve traffic flow and to maximize parking, determining the best location for possible construction of a permanent restroom facility, and evaluating the current ramp to minimize buffering time for loading and unloading vessels.