Project Description
Design and construct a sidewalk on Airport Rd.Project Location
Airport Rd. from where the existing sidewalk end at the entrance of SouthWest Florida Collage to Piper Rd.Latest Updates
The design scope is being done go to purchasing to go out for proposals.Budget
Phase | Cost |
---|---|
Design | $229,500.00 |
Construction | $918,000.00 |
Total Budget | $1,147,500.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 02/01/2024 | 12/30/2024 |
Project Phase
Planning and Project Approval
Last Updated
03/13/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Sponsor Department
Public Works